Sabtu, 30 Maret 2013

RINCIAN ANGGARAN BELANJA (RAB) PEMBANGUNAN REHAB MASJID JAMI NURUSSHALIHAH

Dibawah ini merupakan rincian anggaran belanja (RAB) masjid nurusshalihah. jika ada masukan atau komentar dalam cara kami menyajikan data, harap untuk disematkan dalam kotak komentar dibagian bawah pada blog ini. terimakasih telah berkunjung ke blog ini.

NOURAIANVOLUME & KEBUTUHANHARGA SATUANJUMLAH
IBelanja Barang
1Besi cor Dia 16”M5,60021,500.0120,400,000.0
2Besi cor Dia 06”M6,80021,500.0146,200,000.0
3Besi cor Dia 12"M6,20021,500.0133,300,000.0
4Kawat corKg20021,500.04,300,000.0
5Pasir hitamM3850235,000.0199,750,000.0
6Batu cor 1x1,5"M3650225,000.0146,250,000.0
7Plat Alumunium 0,01”M70115,000.08,050,000.0
8Batu bataBj5,000750.03,750,000.0
9Semen (PC) 50 kgSak6,30055,000.0346,500,000.0
10Semen putih (PC) 50 kgSak8070,000.05,600,000.0
11PakuKg18014,000.02,520,000.0
12Kayu meranti 4x6x4 mM313,900,000.03,900,000.0
13Kayu meranti 8x12x4 mM313,900,000.03,900,000.0
14Kayu kapuk 3x20x4 mLbr30015,000.04,500,000.0
15Kayu jati 5x15x3 mM319,275,000.09,275,000.0
16Kayu jati 7x15x3 mM319,275,000.09,275,000.0
17Tegel keramik lantai 40x60 cm (motif)M238076,000.028,880,000.0
18List ppojok keramik (motif)BH1408,500.01,190,000.0
19Tegel Keramik hias (Kuba)M215567,000.010,385,000.0
20Tegel keramik hias (lantai miring)M214062,000.08,680,000.0
21Kaca hias tebal 5 mmM17095,000.016,150,000.0
22Lem kayu merk RajawaliKg20018,000.03,600,000.0
23Kait jendela lamskar kait kuninganBJ1632,000.0512,000.0
24Engsel jendela kuninganBj3648,000.01,728,000.0
25Bambu bongkotanLjr4558,000.03,640,000.0
26Cat kayuKg4046,200.01,848,000.0
27Cat tembokKg23018,000.04,140,000.0
28Minyak cat tinner ALtr2025,000.0500,000.0
29Tali nelonKg426,500.0106,000.0
30Timba corBh709,000.0630,000.0
31Kabel merk focus TC3M4008,500.03,400,000.0
32Kabel merk focus TC2M6005,800.03,480,000.0
33Stop kontak brocoBh610,500.063,000.0
34Skakel ganda brocoBh5412,000.0648,000.0
35Fetning taman brocoBh8423,000.01,932,000.0
36Fiting donletBh1846,000.0828,000.0
37Lampu sorot pasangBh475,000.0300,000.0
38Lampu gantungan hiasBh1350,000.0350,000.0
39Kipas angin uk. BesarBh6580,000.03,480,000.0
40Sound system MasjidBh21,875,000.03,750,000.0
41Lampu TL 24 wat ( panasonic)Bh3242,000.01,344,000.0
42Lampu TL 13 wat (panasonic)bh7625,000.01,900,000.0
43Lampu TL 9 wat (panasonic)bh621,000.0126,000.0
44Paralon 0,08” instalsiLjr1003,800.0380,000.0
45Paralon L 0,08"Bj100700.070,000.0
46HandbodosBj60500.030,000.0
47T-dosBj120500.060,000.0
J u m l a h I1,251,600,000.00
IIUpah Tenaga Kerja
1Kepala Tukang1HOK24070,000.016,800,000.0
2Wakil kepala Tukang 1HOK24065,000.015,600,000.0
3Tukang15HOK24060,000.0216,000,000.0
J u m l a h II248,400,000.0
J u m l a h I + II1,500,000,000.00



bagi anda yang ingin melihatnya dalam versi excel dan melihat dalam tampilan yang lebih jelas. silahkan download pada link dibawah.